Members of the Lochaber Area Committee have approved a prioritised roads maintenance programme for the area for this year 2021/22.

The programme is based on current priorities.

The Capital budget allocation for Lochaber is £1,237,454, and the agreed priorities included in the approved road maintenance schedule are, for example:

Surface dressing works on the A884 and B8043;

inlay works at East Bay Mallaig, Lundavra Road, Lanark Place and Henderson Row;

Overlay works at Morar village, Mingarry and Torlundy Road;

Patching on various routes including Burnside Road (Strontian), Fersit, Loch Arkaig, Albert Road, and Angus Crescent.

Members were informed that a jetpatcher is hired for a one-month programme to repair urgent potholes prioritised in Lochaber using a cold-lay process of bitumen emulsion and chips.

The Highland roads budget for 2021/22 was approved at the Council’s Economy and Infrastructure Committee on 4 February 2021. 

The total Highland roads capital budget is £17.2M.

The current revenue budget allocation for Lochaber is £1,110,564 which is required to cover labour, plant and materials (including salt) for roads cyclical maintenance and winter maintenance activities.

spot_imgspot_imgspot_imgspot_img
Joseph Kennedy
Joseph Kennedy
Joseph Kennedy is a senior writer and editor at The Highland Times. He covers politics, business, and community affairs across the Highlands and Islands. His reporting focuses on stories that matter to local people while placing them in a wider national and international context.
Latest news
spot_imgspot_imgspot_imgspot_img
Related news